Jeff and Stan:
I lead the group responsible for assuring safe, reliable and timely generation electric interconnections with PG&E's D and T systems. I work closely with Rod Boschee's group that handles gas gen interconnections. I just wanted to check in with Enron to see if the company was still planning to go ahead with the Los Banos project and the Lodi project. It's important we know Enron's plans to assure we conduct the most accurate transmission planning studies possible given the number of projects in the application process, notably at Los Banos. While we have sufficient funds to continue the pending electric study at present, we are unsure of Enron's desires. As for gas interconnection issues, given the discussions about the Lodi project extension, it would be useful to know Enron's intent with that project also. Thanks, Paul Sivley Manager, Generation Interconnection Services
|