fyi...

It is great news to be starting new projects!

HK
---------------------- Forwarded by Hollis Kimbrough/EWC/Enron on 05/15/2002
01:54 PM ---------------------------


Robert Grant
05/15/2002 11:10 AM
To: Hollis Kimbrough/EWC/Enron@ENRON
cc:

Subject: WHITEWATER - LOCATION & FACILITIES FOR SERVICE CREW

Hollis,

Here is the message from Mayura regarding the Whitewater Project.


---------------------- Forwarded by Robert Grant/EWC/Enron on 05/15/2002
11:24 AM ---------------------------


Mayura Botejue
05/07/2002 09:44 AM
To: Dave Schulgen/EWC/Enron@ENRON
cc: John Nemila/EWC/Enron@ENRON, Robert Grant/EWC/Enron@Enron, Ronald
Brzezinski/EWC/Enron@ENRON, Jeff Maurer/EWC/Enron@ENRON, Jeff
Ghilardi/EWC/Enron@ENRON, Erich Ossowski/EWC/Enron@Enron

Subject: WHITEWATER - LOCATION & FACILITIES FOR SERVICE CREW

May 7, 2002

Hello Dave,

WHITEWATER - LOCATION & FACILITIES FOR SERVICE CREW

I believe that now is the time to set the various elements in place for your
department to meet our obligations with regard to service and warranty
support on the project.

The project - located in Palm Springs - will comprise of 41 EWC 1.5 WTGs. The
project site will not have any permanent facilities for operations and
service personnel. The area is not secured and burglary is a major problem.

The EWC SCADA computer will be located within the substation building. The
BOP contractor has requested a total of seven (7) T1 lines at the substation
building for communications. He will make available one of these lines for
use by EWC.

Our service crew trailer and tools container will have to be located off site
in a secure location. We should start looking to rent secure space now. You
will have to notify Robert Grant about the phone line requirements at the
location where your service crew will based.

There will be a project site walk through on May 27. The BOP contractor
expects to have the roads rough graded and the WTG pad locations staked at
this time. You should arrange for someone from your group to be present on
this day to develop familiarity with site and bring up any issues that may
arise.

Best regards,

Mayura Botejue
Project Manager - Whitewater