Mark,

The following list is to be used when compiling the windsystem full power
test. We will use the SCADA 10-average data. Turbines need to be grouped
into bus-groups. So, we will need to aggregate all turbines on the bus and
run the test.

On a separate topic,

We need to apply a similar logic to the existing curtailment program. Thus,
there would be two numbers (Bus-1, and Bus-2). Can you verify if the
existing spread sheets using the 10% correction were outputted. I can use
those to query this list for the historical. If not, we can run the routine
after we make the change for the June report.

Recall, this is the month we need to verify the prorating method by R.S. and
our method. When we run the analysis, we need to compile the curtailment
file into the Feb. format and send to Dave Matson.

Of course, we can talk about running all these. If need be, I or Mark could
run this analysis.

JD
---------------------- Forwarded by Jeff Duff/EWC/Enron on 07/03/2002 12:16
PM ---------------------------


Matt Allsup
07/03/2002 11:03 AM
To: Jeff Duff/EWC/Enron@ENRON
cc: Kurt Anderson/EWC/Enron@ENRON, Mark V Walker/EWC/Enron@ENRON, Mark
Fisher/EWC/Enron@Enron, Phil Waddell/EWC/Enron@ENRON, Guy
Dees/EWC/Enron@ENRON, rkblackshear@aep.com

Subject: Bus list at Desert Sky