Subject:Re: Antwort: Availability Definitions
Cc:
Bcc:
Date:Thu, 7 Mar 2002 05:49:00 -0800 (PST)

---------------------- Forwarded by Hollis Kimbrough/EWC/Enron on 03/07/2002
02:00 PM ---------------------------


Hollis Kimbrough
03/07/2002 01:44 PM
To: Klaus Holtel/DEVELOP/TWT/DE@TWTDE
cc: Ulrich Schomakers/SERVICE/TWT/DE@TWTDE, Benjamin Bell/EWC/Enron@ENRON,
Jeff Maurer/EWC/Enron@ENRON, Jeff Marecic/EWC/Enron@Enron

Subject: Re: Antwort: Availability Definitions

Hello Klaus,

I am trying to do a comparison between the 1.5 MW availability definitions
used in Germany versus the one used here in the US. Per your attached
e-mail, we both use the Enron Availability (EA) definition, however the
definitions are different due to the number of available counters in the PLC
and the placement of the "MT" term in the equations. In Europe you are
limited to 4 counters while the US VisuPro has 7 and in Europe you include
the MT term in both the numerator and the denominator while in the US we only
include it in the denominator but we deduct 4 hours per month as a
maintenance allowance.

With respect to the timers, the differences center on how 8 status timers are
treated which result in a slightly higher availability for US turbines given
the same operating conditions. The status timers are: "Overvoltage",
"Undervoltage", "Underfrequency", "Overfrequency", "Outside Temperature too
low", "Gear oil temp too low", "Line fault voltage" and "Line fault
frequency". In the European EA these values are counted as "Down Time" and
are added in the denominator but not in the numerator resulting in a larger
denominator and therefore a lower overall availability. In the US EA these
terms are added in both the denominator and the numerator thereby resulting
in no change, either negative nor positive.

With respect to the "MT" term, the European EA includes this number in both
the numerator and denominator which means the "MT" term does not affect
European EA regardless of how much time a European turbine stays in
maintenance mode. In the US the use of the "MT" term results in a lower EA
result for values where the maintenance time exceeds 4 hours per month (48
hours per year).

This brings me to my questions:
1. Do the 8 status timers result in very significant impact on the EA term
in Germany and throughout Europe?
2. Can you quantify, in percent EA, the impact of these 8 status timers for
some typical turbines?
3. Can you give me an example of how much "MT" time you accumulate in a
month for a typical turbine?

If you have any other thoughts or ideas on how we might quantify the
differences between the two EA definitions I would like to hear them.

Best Regards,
Hollis


---------------------- Forwarded by Hollis Kimbrough/EWC/Enron on 03/06/2002
03:09 PM ---------------------------


Klaus Holtel@TWTDE
03/06/2002 02:09 AM
To: Hollis Kimbrough/EWC/Enron@ENRON, Ulrich Schomakers/SERVICE/TWT/DE@TWTDE,
Benjamin Bell/EWC/Enron@ENRON, Jeff Maurer/EWC/Enron@ENRON, Klaus
Eilermann/SERVICE/TWT/DE@TWTDE
cc: Klaus Eilermann/SERVICE/TWT/DE@TWTDE, Andrea
Meiners/SERVICE/TWT/DE@TWTDE, Uwe Geisink/SERVICE/TWT/DE@TWTDE

Subject: Re: Antwort: Availability Definitions

Hi Hollis,

in VisuPro we have two different calculations of "EA" = Enron Availability.

One for new VisuPro version and PLC program for USA (Montfort, Klondike, ...)
and the other for the old VisuPro version for Europe.





The Remote Control department use for the montly availability report to Adam
Umanoff the calculation:


Enron Availability: EA[%] = (SOT+ MT) / (SOT+DT+MT+RT) * 100%



Europe:
The running PLC program of the Bachmann controller in Europe supports only 4
Timer:

Timer:
System Ok Time SOT
Down Time DT
Maintenance Time MT
Repair Time RT


Survey Time (ST) = SOT+DT+MT+RT


Availability:
Enron Availability: EA[%] = (SOT+ MT) / (SOT+DT+MT+RT) * 100%




USA:
The PLC program and VisuPro for USA supports 7 Timer:

Timer:
System Ok Time SOT
Down Time DT
Maintenance Time MT
Repair Time RT
Line Out Time LOT
Weather Out Time WOT
External Stop Time EOT

Survey Time (ST) = SOT+DT+MT+RT+LOT+WOT+EOT


Availability:
Enron Availability: EA[%] = (SOT+LOT+WOT+EST) / (SOT+DT+LOT+WOT+EST+MT+RT) *
100%




Kind Regards,
Klaus Holtel & Klaus Eilermann


---------------------- Weitergeleitet von Klaus Holtel/DEVELOP/TWT/DE am
06.03.2002 09:44 ---------------------------


Klaus Eilermann
06.03.2002 09:25
An: Klaus Holtel/DEVELOP/TWT/DE@TWTDE
Kopie:
Thema: Re: Antwort: Availability Definitions

wie besprochen ...
----- Weitergeleitet von Klaus Eilermann/SERVICE/TWT/DE am 06.03.02 09:27
-----

Ulrich Schomakers
05.03.02 21:23

An: Klaus Eilermann/SERVICE/TWT/DE, Andrea Meiners/SERVICE/TWT/DE, Uwe
Geisink/SERVICE/TWT/DE@TWTDE
Kopie:
Thema: Re: Antwort: Availability Definitions

Klaus,
could you please answer that email and explain it correctly, that everybody
understands it. Discuss that with Andrea and Uwe.
Please do that tomorrow.

Thanks
Uli

---------------------- Weitergeleitet von Ulrich Schomakers/SERVICE/TWT/DE am
05.03.2002 09:21 PM ---------------------------


Hollis Kimbrough@ENRON
05.03.2002 07:53 PM
An: Ulrich Schomakers/SERVICE/TWT/DE@TWTDE
Kopie:
Thema: Re: Antwort: Availability Definitions

Uli,

At the bottom of this document there are 4 calculations for availability.
They are Machine, Operational, Line and Enron Availability. Which one of
these availabilities do you include in your monthly reports to Adam when you
are reporting availability?

Best Regards,
Hollis



Ulrich Schomakers@TWTDE
02/22/2002 06:35 AM
To: Hollis Kimbrough/EWC/Enron@ENRON
cc: Benjamin Bell/EWC/Enron@ENRON, Jeff Maurer/EWC/Enron@ENRON

Subject: Antwort: Availability Definitions

Hollis,

here our calculation.



Best regards
Uli






Hollis Kimbrough@ENRON
21.02.2002 07:49 PM
An: Ulrich Schomakers/SERVICE/TWT/DE@TWTDE
Kopie: Benjamin Bell/EWC/Enron@ENRON, Jeff Maurer/EWC/Enron@ENRON
Thema: Availability Definitions

Hello Ule!

In the Senior Management reporting (for Adam) can you provide me a definition
of the availability terms you propose to use? We want to compare them to the
definitions we are going to use to ensure that they are similar.

Right now our plan is to use the Enron Availability definition
(SOT+LOT+WOT+EST)/(SOT+DT+LOT+WOT+EST+MT+RT) from the VisuPro system for the
1.5 MW WTG and the Machine Availability (Op Hours/ Line Hours) for the other
turbines.

Best Regards,
Hollis