Enron Mail

From:drew.fossum@enron.com
To:jeffery.fawcett@enron.com
Subject:Re: Caithness Big Sandy LLC
Cc:susan.scott@enron.com
Bcc:susan.scott@enron.com
Date:Sun, 23 Jul 2000 14:59:00 -0700 (PDT)

Great summary. Sounds like we have plenty to do. Susan, lets talk Monday
and coordinate the law/regulatory stuff. Gracias. DF




Jeffery Fawcett
07/21/2000 12:36 PM
To: Steven Harris/ET&S/Enron@ENRON, Kevin Hyatt/ET&S/Enron@Enron, Julia
White/ET&S/Enron@ENRON, Drew Fossum/ET&S/Enron@ENRON, Mary Kay
Miller/ET&S/Enron@ENRON, Keith Petersen/ET&S/Enron@ENRON, Glen
Hass/ET&S/Enron@ENRON, Terry Galassini/ET&S/Enron@ENRON, Ronald
Matthews/ET&S/Enron@ENRON, Earl Chanley/ET&S/Enron@ENRON, Susan
Scott/ET&S/Enron@ENRON, Darrell Schoolcraft/ET&S/Enron@ENRON, Rod
Hayslett/FGT/Enron@ENRON, Alicia Goodrow/Corp/Enron@ENRON, James
Centilli/ET&S/Enron@ENRON
cc: Lorraine M. Lindberg, Christine Stokes/ET&S/Enron@ENRON, TK
Lohman/ET&S/Enron@ENRON, Michelle Lokay/ET&S/Enron@Enron

Subject: Caithness Big Sandy LLC

TW and Caithness met in Denver this week for the first face-to-face meeting
between the parties. The purpose of the meeting was to review the status of
the Caithness Big Sandy Project and to establish the next steps for moving
the project forward.

Caithness Corporation
Caithness Corp. is a privately held company based in New York with a variety
of business interests. The company is essentially a financial vehicle for
private investors. Their energy segment currently owns 1,200 MW of
generation through renewable assets in California (geothermal at Coso, wind
in Tehachapi and Palm Springs) and a gas fired plant in South Carolina
jointly-owned by Florida Power & Light.

Big Sandy Project
The Big Sandy Project is a proposed power plant to be located near Wickieup,
Arizona. The project would be built in two phases- first phase would be 550
MW, with a gas load of approx. 80,000 MMBtu/d, and phase 2 would add another
170 MW for a total of 720 MW with a gas load of 120,000 MMBtu/d.

The proposed location of the plant is approximately 40 miles south of
Transwestern's pipeline. The take-off point on Transwestern would be at/near
valve station #1008, approximately 15 miles downstream of compressor Station
#1. The current estimate includes an alignment that follows Arizona state
highway 93 south to a location 2 miles southeast of Wickieup in the S/W 4 of
Section 5, T15N, R12W, Mohave County, Arizona. There is a 500 KV
transmission line owned by WAPA that crosses the property. This line is one
of the principal electric transmission systems in the Southwest and extends
from the Phoenix area to the Mead substation near Boulder City, NV. I've
included a WAPA map below which indicates this line. Also, on the site is a
water pipeline owned by the Cyprus Amax Bagdad mine. Water for the plant
will come from an encapusulated water table through deep wells. They have
currently dug the first two test wells, each capable of 500 cfm. The power
plant will require approximately 3,500 cfm of water. In addition to the
wells, the plant has several thousand-acre feet of water rights to surface
water from the Big Sandy River. The project may also purchase water from the
Cyprus Bagdad water pipeline.

The chief geological feature of this area is the Big Sandy River and
associated wash. The highway 93 roadbed follows along the river. The area
includes rolling hills and is principally desert terrain, with some limited
agricultural and ranching interests. Wickieup is a very small town with an
estimated population of 200.

Project Schedule
Gas Turbine(s) ordered Westinghouse-Seimens May 2000
Submit Environmental Impact Statement (EIS) August 2000
Arrange financing December 2000
EIS approval March 2001
Construction begins April 2001
Testing begins July 2002
Commercial Operation November 2002

There are two lead agencies for purposes of the project's EIS- the Bureau of
Land Management (BLM Kingman office) and the Western Area Power
Administration (WAPA). There is only one endangered/threatened species known
to be present in the area.

Lateral Pipeline Alignment
The most critical path item is the alignment of the lateral pipeline. The
alignment (lateral pipeline route) must be included in the EIS to be filed
next month. Caithness has spoken preliminarily with the Arizona Department
of Transportation (ADOT) and the agency is amenable to granting an easement
for the pipeline. The problem appears to be in the limited amount of right
of way available. Measured from the shoulder to the fenceline, there is only
a 70 ft. right of way available for construction. Typically, pipelines
require a 100 ft. temporary construction easement and 50 ft. of permanent
right of way. Preliminary discussions indicate another problem with this
alignment may be the roadway's routing within the wash of the riverbed.

If the highway 93 corridor is unsuitable for the pipeline, the second
alternative appears to be running the pipeline down the adjacent N/S section
line. The problem with this approach is that as the line nears the site, the
routing would have to contend with the river bed and wash areas, possibly
necessitating deep burial and anchoring. The other route would involve
following along the WAPA electric transmission corridor. The only issue
there, aside from whether WAPA would permit the pipeline encroachment, is
whether there are safety and/or corrosion concerns associated with a high
pressure gas line located under a high voltage transmission system.

Other Preliminary Project Issues
There are other fundamental issues to address. The original concept was to
interconnect the proposed Transwestern lateral with El Paso's northern
mainline and the yet-to-be-constructed Questar Southern Trails Pipeline, both
of which lay adjacent to Transwestern's mainline. Transwestern's original
estimate to construct a 16" lateral pipeline and meter station ($20.3MM) was
based on the following specifications:

120 MMcf/d
450 psig delivery pressure,
900 psig inlet pressure

The meeting resulted in a revised set of specifications that now include a
higher 550 psig minimum delivery pressure (new technology Westinghouse
turbines). In addition, our understanding is that EPNG's system operates at
a pressure 100-150 psig lower than Transwestern's. In order to accommodate
EPNG deliveries and to account for the new higher minimum pressure, the
design will likely change to a 20" pipeline.

Next Steps (responsible party/department)
Task Date Due Party/Dept.
Pipeline Alignment
1. Estimate to plot lateral pipeline route. 8/4 Matthews/Chanley
2. Engineering services agreement 8/4 Scott/Fawcett
3. Final alignment sheets. 8/25 Matthews/Chanley

Misc. Items
1. Confidentiality Agreement 7/24 Scott/Fawcett
2. Data items to Caithness
- Form 567 7/26 Matthews
- Gallup FERC filing (flow diagram) 7/26 Scott
- Sta. 1 and Needles flow/pressure data 7/28 Matthews
- Outage reports/maintenance schedules 7/28 Matthews

Engineering/Design
1. Original estimate (16" line) to Caithness 7/24 Matthews
2. Revised specifications to Transwestern 7/28 Caithness (T.P.)
3. Revised estimate (20" line) to Caithness 8/4 Matthews/Chanley

Other Issues
Several key issues need to be addressed concurrently with the pipeline
alignment and engineering activities:

Task Date Due Party/Dept.
Deal Structuring
1. Financing/cost amortization 9/8 Fawcett/Hayslett
/Centilli/Goodrow
2. Research interconnect policy (EPNG) 8/4 Scott/Regulatory
3. Research 7© application requirements 8/11 Scott/Regulatory
4. Rates 9/22 Scott/Regulatory
/Centilli
5. Research open season requirements 8/18 Scott/Regulatory

The above list is certainly not meant to be all-inclusive and a kick-off
meeting to discuss the project schedule will be put together shortly. In the
meantime, if you have any questions regarding this project, please let me
know. Also, please feel free to forward this memo to anyone I've
inadvertently left off the distribution. Thanks.