I'd prefer that we give them a high level bullet point type summary rather
than a draft of the filing itself. DF





From: Susan Scott 07/18/2000 10:12 AM


To: Mary Kay Miller/ET&S/Enron@ENRON
cc: Drew Fossum@ENRON, Glen Hass/ET&S/Enron@ENRON, Mary
Darveaux/ET&S/Enron@ENRON, Shelley Corman/ET&S/Enron@ENRON

Subject: Re: TW Capacity Options

As I have mentioned already a couple of times, the Commercial Group feels it
is important to have something to present to customers. My concern is that
if we just tell them about it over lunch or over the phone, something is
going to be ignored or lost in the translation, and then we'll have a dozen
protests to contend with. Surely we've presented new services to customers
before in advance of filing...if so, how did we go about it?

Also, are you OK with filing July 31, or just as soon as we can get a
prefiling conference with FERC?







From: Mary Kay Miller 07/18/2000 10:06 AM


To: Susan Scott/ET&S/Enron@ENRON, Drew Fossum
cc: Glen Hass/ET&S/Enron@ENRON, Mary Darveaux/ET&S/Enron@ENRON

Subject: Re: TW Capacity Options

I'm going over it and hope to have comments to you shortly- we don't usually
share the draft, just the concept which I don't see any hold up on that, but
since we're still working on it, I don't want to give them a hardcopy- MK





From: Susan Scott 07/18/2000 09:59 AM


To: Glen Hass/ET&S/Enron@ENRON
cc: Mary Kay Miller/ET&S/Enron@ENRON, Mary Darveaux/ET&S/Enron@ENRON

Subject: Re: TW Capacity Options

I spoke with Steve Stojic about this and he had the same concern. Even
though I was trying to keep this out of the new rate schedule requirements by
not making it a rate schedule, I believe I still managed to cover many
checklist items. One that is not covered is testimony similar to what might
be filed in a rate case, in order to justify market based rates. We are
planning to include a revenue estimate. I'll go over these and make sure
everything is addressed before filing.

Are you OK with this filing from a general conceptual standpoint? The
marketers want to start giving a draft to customers for them to review
beginning TODAY.






From: Glen Hass 07/17/2000 05:35 PM


To: Susan Scott/ET&S/Enron@ENRON
cc: Mary Kay Miller/ET&S/Enron@ENRON, Mary Darveaux/ET&S/Enron@ENRON

Subject: Re: TW Capacity Options

Susan,

In reviewing the proposed filing I had some questions. On page 2 in the
discussion of ensuring sufficient capacity we offer to establish position
guidelines, do we need to outline these and either include them as an exhibit
or have them ready for reply to either protesters or a staff data request?
Secondly, if we regard this as a new service does our filing comply with all
aspects of 154.202 (a) (ii), (iii), (iv) (A) & (B), (v), (vi), (viii) and
(ix)? In recent filings the staff has challenged our filings in terms of
addressing each of these requirements. I believe many our covered but
thought you might like to double check for compliance. What about a revenue
estimate? Seems like we need one, even if its still very speculative.

Glen





From: Susan Scott 07/12/2000 03:19 PM


To: Steven Harris/ET&S/Enron@ENRON, Jeffery Fawcett/ET&S/Enron@ENRON, Kevin
Hyatt/ET&S/Enron@Enron, Lorraine Lindberg/ET&S/Enron@ENRON, TK
Lohman/ET&S/Enron@ENRON, Michele Lokay/ET&S/Enron@Enron, Christine
Stokes/ET&S/Enron@ENRON, Bill Cordes/ET&S/Enron@ENRON, Mary Kay
Miller/ET&S/Enron@ENRON, Julia White/ET&S/Enron@ENRON, Shelley
Corman/ET&S/Enron@ENRON, sstojic@gbmdc.com, Mary Darveaux/ET&S/Enron@ENRON,
Glen Hass/ET&S/Enron@ENRON, Drew Fossum@ENRON, John
Buchanan/ET&S/Enron@ENRON, Ramona Betancourt/ET&S/Enron@ENRON
cc: Tony Pryor/ET&S/Enron@ENRON, Brian Hensley/ET&S/Enron@Enron

Subject: TW Capacity Options

Attached for your review is a draft of Transport Options filing that
incorporates the comments and suggestions I've received since last week.
Please provide any further suggestions/changes to me as soon as possible, but
in no case later than close of business, Friday, July 14.

The timeline I've discussed with TW Commercial for this project is as follows:

Final draft comments Friday, July 14

Circulate draft to customers,
customer meetings, time for
customers to respond, informal
discussion with FERC Mon. July 17 - Wed. July 26

Final internal review/edit of filing Thursday, July 27

FERC filing Monday, July 31

Please let me know your comments on this proposed timeline as well. Thank
you.