-----Original Message-----
From: =09Graves, Jerry =20
Sent:=09Wednesday, November 14, 2001 8:09 AM
To:=09Alexander, James C.; Blair, Lynn; Bonnstetter, Mike; Boothe, David; B=
oston, Jerry; Brown, Sharon; Bryant, Mike; Buchanan, John; Burns, Christoph=
er; Clark, Scott; Cordes, Bill; Corless, Gary; Corman, Shelley; Geaccone, T=
racy; Gilbert, Tom; Good, Chuck; Gottsponer, Morgan; Graham, Charlie; Grave=
s, Jerry; Harris, Steven; Hood, Colleen; Howard, Randy; January, Steve; Jol=
ly, Rich; Jordan, Fred; Keller, John R.; Kowalke, Terry; Kudym, Judy; Kuehl=
, Toby; Lawrence, James; LeBeau, Randy; Lowry, Phil; Maestas, Gary; Mall, G=
reg; Martens, Donna; McGillivray, RR; Moore, Jan; Morse, Ronnie; Nelson, Mi=
ke; Neubauer, Dave; Odneal, Dave; Rice, Randy; Roensch, David; Schoolcraft,=
Darrell; Schroeder, Jim; Smith, Rick; Spraggins, Gary; Stephens, LD; Swett=
, Larry; Thomas, Steve; Watson, Kimberly; Williams, Jo; Williams, Walt; Abd=
moulaie, Mansoor; Alters, Dennis; Dushinske, Adam; Faucheaux, Eric; Frazier=
, Perry; Gilbert, Maurice; Hughes, Matt; Matthews, Ron; Ramsaran, Gale; Smi=
th, Buzz; Anderson, Ken; Aschwege, Doug; Beck, Judy; Descoteaux, Carolyn; D=
obbins, Dan; Johnson, Robert L.; Kolarik, David; Reinecke, Bryan; Sans Souc=
i, Becki; Westfall, Roger; Asante, Ben; Choquette, Gary; McChane, Bob; Stur=
n, John; Wirasinghe, Errol
Subject:=09Outage Commericial Review Meeting (NNG,TW, & NBPL)


FYI,

The next Outage Coordination Commercial Review meeting is 11/14/01. The pu=
rpose for the meeting is to discuss outages that have a flow impact for the=
month of December. Please review the attached outage report. If you have a=
ny questions, please give me a call. =20

=20

Jerry Graves=20
713-345-8923

When: November 14
Time: 1:00 to 2:00
Where: Houston 49C2
Omaha VCR - 7th floor
Field - Conference # 877-795-3687 =20
Code # 755555


NORTHERN BORDER PIPELINE=09
=09 =09 =09 =09 =09
=09Location=09Date=09Scope=09Comments=09
NB=09CS11=0912/03/01 to 12/03/01=09 Scope/Wash, MP2, and Cooler mods.(10 hr=
s)=09Potential impact is low.=09
NB=09CS07=0912/13/01 to 12/13/01=09 Maintenance/Wash, MP2, and Cooler mods.=
(10 hrs)=09Potential impact is low.=09
NB=09CS03=0912/11/01 to 12/11/01=09 Wash, MP2, (10 hrs)=09Potential impact =
is low.=09