Do we need anyone to test the earnings portion?

-----Original Message-----
From: =09Lebrane, Pamela =20
Sent:=09Monday, September 24, 2001 11:25 AM
To:=09Beltri, Angeles; Pham, Becky; Sheffield, Sandy; Frazier, Steve; Geacc=
one, Tracy; Erwin, Jill; Clement, Jody; Baxter, Bryce; Dawes, Cheryl; Horn,=
Cindy; McAndrew, Anna; Joslyn, Kate; Adams, Laurel; Leskowitz, Mark J.; Mc=
clure, Mark; Ratnala, Melissa K.; White, Melissa; Bruce, Michelle; Sammon, =
Robert; Shore, Geraldine; Millerchip, Rebecca; Wynne, Rita; Behn, Mary; Dwo=
rsky, Mildred; Shoup, Cynthia; Sengele, Julia; Chapman, Neil; Youngson, Kar=
en; Davis, Kasey; Moseley, Debbie; Johnson, Alice; Burns, Donna; Bell, Step=
hen; Perkins, Raewyn; Schumacher, Phillip; Umphreys, Tom; Flanery, Sharon; =
Daniels, Diane; Lin, Judy; Centilli, Carolyn; Woerlen, Carol; Prendergast, =
Pat; Griffiths, David; Pool, Deelyn; Nightingale, Ron; Gunn, Cephus; Spoede=
, Amy; Cockrell, Rainier; Hanson, Kristen J.; Allen, Thresa A.; Lessor, Jam=
es N.; Patterson, Grant; Hanslip, David; White, Angela; Dozier, Scott; Myer=
s, Donnie; Garcia, Jorge A. ; Cash, Larry; Pham, Vivien; May, Kevin; Cagney=
, Patrick; Schwarzbach, Stephen; Blaskowski, Carrie; Mayeux, Cassandra; Van=
dor, David; Walters Jr., Harry; Kaster, Mei-Ling; Tran, Agatha; Tran, Joann=
e; Green, Alisa; Kathol, Sherri; Project Sunrise Reports Factory
Cc:=09Johnson, Jan; Kanani, Pratish; Nelson, Emitra; Fennessy, Beverly; Sch=
midt, Mark; Frank, Mark; Reed, Jennifer; Chan, Li N.; Lykes, Kate; D'souza,=
Rena
Subject:=09Project Sunrise September 30 Go-Live FIT 1 Status

FIT1 for AR_AP and Earnings products completed. AR Aging, AP Aging, Vendor=
Spend and Profit Center reports tested.

AR_AP user testing
14 users from several business units participating- ENW, ETS, ENA, EIM, COR=
P, EGM, EBS.
Houston and Canada users involved.
17 company codes successfully tested.
Errors related to inappropriate calculation of due dates for aging and fore=
ign currency reporting. Aging error resolved.=20

Earnings user testing
6 users from several business units participating - EGAS, EGM, ENA.
Successfully completed one of two scheduled sessions. Session cancellation=
due to slow system performance resulting from concurrent ACTA job run.
Profit Center reporting tested.


Coming this week:
Earnings FIT2 on Tuesday, September 25. FIT2 will test Profit Center and C=
S reports.
AR_AP FIT2 on Wednesday September, 26. FIT2 will primarily focus on testin=
g Receipts on Time and Cash Collection Percentage reports.


Lots of hard work went into the activities leading up to the successful fir=
st iteration of user testing. Thanks to the technical developers, report d=
evelopers, analysts, DBA, business analysts, ISC consultants, SMEs, busines=
s unit coordinators, and product managers.


Regards,
Pamela