fyi...
-----Original Message----- From: Terech, Henry Sent: Wednesday, August 01, 2001 5:27 PM To: Daily, Pamela Cc: Akhave, Billie; Soyal, Tara Subject: ETS Remodel Budget-Y2002 Pam- The following is a summary of estimated costs for the remodel and occupancy of Levels 39-46 in ECN. These are present estimates and ETS would receive formal, hard budgets at project inception and only be charged actual costs: Construction: $3,500,000 Design: $350,000 Churn: $250,000 Furniture: $1,150,000 Contingency: $250,000 Total: $5,500,000 Please feel free to set a meeting time with Tara should you want to discuss details. Regards- Henry
|