Sonoran Pipeline - KMI should have an offer to us during the week of 10/1.
ROW - Left message for AZ Public Service ROW agent to discuss use of water line as possible route for gas line to serve Red Hawk plant.
Cost estimate - Agreed with engineering to delay cost estimate until 10/2. Preliminary indications are we will need to begin scaling back cost beginning with compression.
Marketing -
Duke - Waiting for response, left message 9/28.
AZ Public Service - Total gas consumption across 2 plants estimated to be 380,000 MMBtu/d by 2004. Their Red Hawk plant is adjacent to the Duke Arlington plant. Plan to meet in Phoenix week of 10/8 after cost estimate complete.
Sempra - No respsonse yet, left message 9/26.
Cost estimate prepared for initial Environmental work for FERC filing - $9.4mm.
Preparing risk analytics / mitigants for RAROC
Joe Hartsoe / Nancy Bagot will monitor El Paso FR case (RP00-336) and report on further studies and answers questions posed at 24 Sept conference or in writing
- Initial comments (on all capacity allocation issues and procedural recommendations): Oct. 15
- Reply comments: Oct. 26

Kingman CS heat recovery project
Mojave requested firm pricing; ETS awaiting revised cost estimate from ABB to compare with internal estimates.
PPA term sheet (rev. #3) forwarded to legal for review/comment - plan to release to Mojave during week of 10/1

Pipeline expansion to Georgia and Alabama
Still progressing analyses
Co-ordinating with Dowd on Wolverine

Alaskan Northwest Natural Gas Transportation Company
Partially executed CA with TCPL, Foothills, Westcoast, and ANNGTC; final execution imminent
Assembled ETS project team
Due diligence team in Calgary during week of 1 Oct
Draft MOU undergoing internal review; comments due Monday.

McNeil Bullet (B==<C segment of Alaska gas pipeline)
Technical concept: 2-3 BCF/d pipeline along NBP r-o-w to transport Alaska gas to midwest markets (Chicago)
Develop Heads of Terms for 50/50 jv between TCPL and Enron
Analyze merits of including El Paso in the jv; legal to check potential market dominance issues contained in FTC consent decree on El Paso merger.
Follow-up meeting with TCPL in ~10 days

Trailblazer
Advised EGNG that KMI was preparing a bid for ETS equity share.
Mike McGowan prepared analysis of CIG-Trailblazer-NNG mainline concept to compete with Coco expansion project.

Pacer (Omaha)
[to follow]

FPL 1750 MW RFP
ETS withdrew from RFP process
ETS and ENA progressing discussions wrt co-development of the Deerfield site (3+1 configuration, 822 MWs)
ENA submitted multiple bids

Storage business development
Following CBR, Paul Bieniawski (prospective team recruit) to prepare storage business plan in consultation with Kent Miller et al.

Consulting support