Enron Mail |
Kevin
I have completed the following costs for the MAOP facility requirements project but have not completed yet the cost of 55,90 and 115 mmcf/d alternatives on the San Juan Lateral. Presently Working with Engineering on this project. Mansoor ---------------------- Forwarded by Mansoor Abdmoulaie/ET&S/Enron on 05/10/2001 03:36 PM --------------------------- Mansoor Abdmoulaie 05/09/2001 03:32 PM To: Morgan Gottsponer/ET&S/Enron cc: Eric Faucheaux/ET&S/Enron@Enron, Perry Frazier/ET&S/Enron@ENRON, Earl Chanley/ET&S/Enron@ENRON Subject: Cost Estimate for MAOP facility requirements Level-A Cost Estimate Cost to replace 30" mainline valve assy with blowdowns and asso piping: $210,000.0 *Gas lost is not included in the cost if blow down required. Cost to do a 30" stopple project: $100,000.0 *By-pass is not required for stoppling activities. *One stopple fitting only. *Gas loss not included in the cost if blow down required. Cost/ mile to replace 30" pipe that would meet class- 3 requirements: $1,166,000 to $1,475,000 (loop with existing).
|