Thanks to all for a productive meeting.
Here's the synopsis. Please let me know if I've missed anything. 1. Anticipated MAOP changes Bloomfield to Bisti - from 1200 to 1250 psig Bisti to Gallup - from 1200 to 1330 2. Impact of these pressure changes on volumes - Morgan to Kevin by 4-27 3. Economic impact of volume increases - Kevin to group by 5-1 4. Review horsepower to determine if any changes may be needed - Planning 4-27 5. Confirm cooler capacity and pressure rating - Planning 4-27 6. Confirm confidentiality and get estimate for 3rd party assistance - Max by 4-25 7. Review technical approach and aspects - Max, Will, Peter by 4-27 8. Next meeting - May 1 2:00 pm (location TBD) At this meeting, we will review results above and make a go/no go recommendation If favorable, initiate discussions with OPS Dave
|