Enron Mail

From:christi.nicolay@enron.com
To:john.moore@enron.com, bill.moore@enron.com, marchris.robinson@enron.com,kathleen.magruder@enron.com, patrick.hanse@enron.com, tom.dutta@enron.com, greg.woulfe@enron.com, bill.rust@enron.com, kevin.presto@enron.com, lloyd.will@enron.com, mary.hain@enro
Subject:Aquila v. Entergy
Cc:richard.shapiro@enron.com, joe.hartsoe@enron.com,richard.ingersoll@enron.com, charles.yeung@enron.com, james.fallon@enron.com, mike.curry@enron.com, rogers.herndon@enron.com, steven.kean@enron.com, elizabeth.sager@enron.com, janine.migden@enron.com,
Bcc:richard.shapiro@enron.com, joe.hartsoe@enron.com,richard.ingersoll@enron.com, charles.yeung@enron.com, james.fallon@enron.com, mike.curry@enron.com, rogers.herndon@enron.com, steven.kean@enron.com, elizabeth.sager@enron.com, janine.migden@enron.com,
Date:Wed, 15 Mar 2000 07:37:00 -0800 (PST)

On 3/30/98, Aquila filed a complaint at FERC against Entergy that Entergy
reserved all of the firm import capacity (2000 MW) at four key interfaces,
even though Entergy did not designate any off-system network resources to
cover these reservations. Aquila's transmission requests were denied or
curtailed causing it to suffer financial losses. Entergy responded that
Aquila had a "fundamental misunderstanding" of Order No. 888 et seq. and that
a transmission provider may deny tariff requests, if that transmission
provider's own reservations "are based on the legitimate reliability needs"
of its bundled retail customers.

Reservation facts: Entergy posted on its OASIS site that it reserved 2000 MW
of capacity at its interfaces with TVA (1100 MW), Southern (400 MW), Arkansas
Electric Coop (250 MW), and Union Electric (250 MW) under the label "Firm
Import for Native Load." Entergy did not designate network resources in the
same manner that it required from Aquila and other network customers.
Entergy explained that its reservations were needed "to meet the immediate
reliability needs of the Entergy System and to accommodate native load growth
over the next few years." (Entergy later told FERC that this was needed for
"current loads" only--not future growth.)

Entergy argued to FERC that it is able to satisfy its generation reserve
requirements, while maintaining lower amounts of generating capacity within
its control area, only because it can rely on the 2000 MWs at issue to reach
neighboring control areas, therefore this is "a legitimate reliability
need." Entergy then claimed that Sec. 28.2 of the pro forma tariff (that
requires a transmission provider, on behalf of its Native Load Customers, to
designate its network resources in the same manner as any Network Customer)
does not apply to a utility's uses of its transmission system to serve
bundled retail customers.

In a draft order issued today, FERC disagreed with Entergy and found that
Entergy reserved virtually all of the firm capacity on four key interfaces,
even though it had no off-system network resources. Instead, Entergy used
its firm transmission reservation to purchase power whenever it was
economical. Entergy denied all other firm transmission requests and
entertained non-firm transmission requests only when it was unable to make an
economic deal for itself. Even though Entergy is not required to take
transmission under its tariff for retail load, it is required to designate
network resources and loads. The off-system resource must be generation
owned by the transmission provider or under contract.

Although FERC found that Entergy violated the OATT and normally the
transmission should be released, Entergy has now begun to designate network
resources (these new procedures are pending at FERC). Aquila also asked FERC
for its financial losses of $281,000, but FERC said it lacked authority to
order money damages. FERC would order refunds of the transmission rate, but
Aquila did not allege that it paid for services it did not receive.

Interestingly, FERC told Aquila that it could bring this matter up in Entergy
Power Marketing's currently pending 3 year update of its market-based rates
stating that use of the transmission system on a non-preferential basis is a
fundamental condition for market-based rates. (Entergy argued against this
saying that there was no allegation that it had profited. FERC rejected this
argument.) Dynegy has already protested Entergy's 3 year update stating that
Entergy is exercising market power by limiting new generation through poor
interconnection procedures and agreements. Enron filed one sentence support
of Dynegy's protest. I think this is why Entergy recently filed its
interconnection agreement and procedures at FERC.

Comm. Herbert dissented saying that this was a "technically" from several
years ago.

Watch for this type of activity from other providers.