Enron Mail

From:victor.lamadrid@enron.com
To:robert.allwein@enron.com, scott.goodell@enron.com, meredith.homco@enron.com,robert.superty@enron.com, f..brawner@enron.com, jonathan.mckay@enron.com, andrea.ring@enron.com, judy.townsend@enron.com
Subject:FW: Sentinel Project
Cc:clarissa.garcia@enron.com, chris.ordway@enron.com, chuck.ames@enron.com,jared.kaiser@enron.com, scott.neal@enron.com, craig.taylor@enron.com, frank.vickers@enron.com
Bcc:clarissa.garcia@enron.com, chris.ordway@enron.com, chuck.ames@enron.com,jared.kaiser@enron.com, scott.neal@enron.com, craig.taylor@enron.com, frank.vickers@enron.com
Date:Thu, 14 Feb 2002 14:59:10 -0800 (PST)

fyi

-----Original Message-----
From: CustomerNotices, WGPHOU [mailto:WGPHOU.CustomerNotices@Williams.com]
Sent: Thursday, February 14, 2002 3:55 PM
Subject: Sentinel Project


February 14, 2002

To: Interested Parties

Re: Sentinel Expansion Project

Transco is developing an expansion of its pipeline system
in the Northeast U.S., referred to as the Sentinel
Expansion Project, and is considering market-area receipt
points at Leidy, Pennsylvania, and the Cove Point LNG
facility in Cove Point, Maryland. While preliminary
analysis indicates that the project capacity would be
approximately 250 Mdt/d at an estimated capital cost of
up to $300 million, the ultimate project design and capital
cost will largely depend on the results of an open season
for the project. Transco is contemplating a target
in-service date for the project of November 2004.

For questions regarding the Sentinel Expansion Project
contact Nancy Hargrove at (713) 215-2926.