Scott,

Structuring got back to us with some issues we need to clarify to get the
pricing from a trader.

Capacity
- Will Calpine be able to get manufacturer's guarantee for net capacity (or
can we re-sell turbines to third party?)
- Is it "unit contingent call" or there will be a "liquidated damage
protection" within the tolling agreement?

Nodal pricing
- What is the exact name of substation in eastern PJM? Structuring could not
find "Parlin" in eastern PJM (even within eastern PJM, there will a
substantial pricing differential among different bus points).

Gas delivery point

Actually, it is really hard to get the number by today since a trader who
will give pricing is not here today. If we don't hear from you or/and if you
don't decide yet about above issues, we will make assumptions as follow;

- Capacity: 180 MW out of 4 LM-6000 turbine with manufacturer's guarantee and
with term of liquidated damage protection included.
- Exact substation: East Hub in PJM
- Gas delivery point: Transco Zone 6

We will try to get the pricing hopefully by tomorrow. Please call me at
713-853-7330, if you have any question. Thank you.