FYI

-----Original Message-----
From: Phillips, George
Sent: Wednesday, June 13, 2001 6:55 AM
To: Carter, Pamela; Ruffer, Mary Lynne; Stokley, Chris
Subject: Meter Operations Update


---------------------- Forwarded by George Phillips/HOU/EES on 06/13/2001 08:53 AM ---------------------------


ppriest2@csc.com <mailto:ppriest2@csc.com< on 06/12/2001 02:48:24 PM
To: george.phillips@enron.com <mailto:george.phillips@enron.com<
cc:
Subject: Meter Operations Update


---------------------- Forwarded by Patricia G Priestley/CEG/CSC on
06/12/2001 02:49 PM ---------------------------


Patricia G Priestley/CEG/CSC
06/12/2001 02:47 PM

To: dhuddles@enron.com <mailto:dhuddles@enron.com<, mwinter@enron.com <mailto:mwinter@enron.com<, rsmoot@enron.com <mailto:rsmoot@enron.com<,
cpelchat@enron.com <mailto:cpelchat@enron.com<
cc: Dionne L Williams/TMG/CSC@CSC <mailto:Williams/TMG/CSC@CSC<, Jo Ellen Campbell/TMG/CSC@CSC <mailto:Campbell/TMG/CSC@CSC<

Subject: Meter Operations Update

Attached is a summary of the impacted areas and a current status of Meter
Operations due to Houston flooding:

Meter reading and posting of data - We are currently unable to read/post
interval data for California or Phoenix. While the electricity has been
restored, phone lines are still inoperable meaning we are unable to read
phone or wireless meters. Since the phone system to the building had
extensive water damage, we are not sure when the lines will be available.
Backup operations are being developed in Dublin but are not yet functional.

Settlements for EEMC - Files for EEMC have been posted through Sunday, the
10th, for day 41, April 30. Day 41 files for 5/1 due Monday, the 11th, and
5/2 due today, the 12th, have not been produced. We are unable to
communicate with our servers because of the phone outage and are therefore
unable to create the files remotely. Through today we have been denied
access to our building. Our plan is to seek access on Wednesday at least
long enough to generate our files and submit them remotely using a laptop.

Settlements for EESO - Files for EESO have been posted through Sunday,
settlement file 4/30 for day 41. We are able to generate settlement files
offsite and are working to submit Monday's 5/1 and Tuesday's 5/2 file by
midnight today.

My plan is to produce these daily updates until all of our operations are
back in place and on schedule.